Deep Basement Excavation in progress at Prince f Wales Drive, Battersea, London - CGL Project

Prince of Wales Drive, Battersea, London

Joseph Slattery

Technical Director

Tel: +353 (0)1 554 6210

Email Joseph

Client

Ground Construction Limited (GCL), on behalf of St William

Services

  • Ground movement analysis
  • Finite element modelling
  • Piling design
  • Temporary works design and design checking
  • Monitoring strategy and contingency planning
  • Slope modelling

 

Work in progress of a Double Deep Basement Excavation, Prince of Wales Drive, London - CGL Project
Finite Element modelling of to assist design of the buttress pile system at the  Double Deep Basement Excavation, Prince of Wales Drive, London - CGL Project

Innovative Temporary Works Buttress Pile system for a Deep Basement Excavation in London

Ground Engineering Awards 2018 - 10th Anniversary Finalist - Prince of Wales Drive - CGL Project CGL has designed a temporary buttress pile support system to prevent collapse of a retaining wall at a second deep basement excavation in London.

CGL was commissioned by Ground Construction Limited to undertake detailed geotechnical analysis for the proposed system to support a section of secant pile wall during basement excavation at Prince of Wales Drive, Battersea, London.

The proposed redevelopment of the site includes construction of 11 mixed-use buildings up to 26 storeys high. A single storey basement is proposed across the site, locally extended to a double deep storey basement in the south east corner where the buttress piling solution was adopted. The site was historically occupied by four gasholders which have been infilled. Sensitive infrastructure constraints exist beyond the SE corner of the site, comprising a Network Rail Viaduct and National Grid Pressure Reduction Station.

“A well considered, planned and executed scheme that delivered significant benefits within the constraints of the project”

Ground Engineering Awards Judges

Given the relatively complex soil structure interaction associated with the temporary buttress pile system, the full section of wall was modelled using PLAXIS 3D (Finite Element) analysis software to assess deflection, bending moment and shear force in the pile wall and buttress system.

The buttress pile system supports a secant pile wall within an excavation down to 10.5m below ground level. The buttress piles act with the secant pile wall, through a rigid connection in the form of a capping beam between both elements. This increases the rotational and lateral stiffness of the wall and provides overall stability and serviceability.

As a value engineered solution, the buttress pile system superseded the original conventional proposal to construct a temporary earth berm and install a large network of steel propping and thrust blocks. This revolutionary approach proved to be a cost effective and practical solution in comparison to conventional propping systems.  Additionally, the buttress pile solution facilitated bearing pile installation to be undertaken from a lower dig level and the overall construction programme was accelerated by eliminating restricted working spaces within the excavation.

CGL is working to implement similar buttress pile systems on other projects to maximise working space and provide other efficiencies.

 

Temporary Works Buttress Pile Support System at Prince of Wales Drive, London - CGL Project